RYMEL Ingeniería Eléctrica S.A.S. officially announces the start of construction of its new industrial plant in June 2025, located in El Noral, municipality of Copacabana, Antioquia.
What does the project consist of?
The project, called Rymel Plant 4, is being developed on a 26,078 m² site, with a projected constructed area of 11,339 m². This new structure will specialize in the manufacture of conventional single-phase transformers for pole-mounted installation.
Objective: expansion and efficiency
The project is part of the company's strategic expansion and strengthening plan, which seeks to increase its operating capacity and respond more efficiently to domestic and international market demand.
Progress and execution schedule
Construction began in April 2025 and is currently in the earthwork phase. The next stages will include:
The estimated completion date of the project is June 2026.
Expected benefits
With this expansion, RYMEL will double its production capacity, improve its delivery times, meet domestic demand more efficiently and strengthen its international presence .